PROJECT IL BOSCO  |  CONFIDENTIAL  |  NOT FOR EXTERNAL CIRCULATION
⚠ PROVISIONAL DATA — All figures subject to DGJ cost opinion (16 Oct 2026)

Model Quality Control

Two gates run live against the current inputs. Section A tests whether the model is internally consistent. Sections B and C test whether the evidence behind it is strong enough for the figures to be relied on at the gate review.

A · Structural integrity

7 of 15 checks passing

Model is not clear for issue. Resolve the failing checks below before circulating figures.

#CheckValueResult
1Total units reconcile to unit schedule40 unitsPASS
2Absorption schedule sums to total units40 / 40PASS
3NIA efficiency within 72–82%67.0%FAIL
4GDV greater than zeroJOD 8,333,850PASS
5TDC greater than zeroJOD 11,284,413PASS
6Hard cost / sqm GFA within JOD 750–1,200JOD 917PASS
7TDC / sqm GFA within JOD 1,000–1,600JOD 1,736FAIL
8GDV / sqm NIA within JOD 1,800–3,000JOD 1,710FAIL
9Return on Cost meets 15% target-28.3%FAIL
10Net Development Profit positiveJOD -3,198,910FAIL
11Substructure contingency ≥ 15%20.0%PASS
12Funding coverage ratio ≥ 1.10x0.27xFAIL
13Ops Year 1 cost / sqm NIA within JOD 15–25JOD 46FAIL
14Cash flow closes to zero balanceJOD -3,146,511FAIL
15S&M budget exceeds commission floorJOD 546,046PASS

B · Evidence confidence gate

Applies decision register item 5 — Medium confidence may sit in the base case with disclosure; Low confidence sits in sensitivity only — together with the P→M threshold for material revenue inputs (item 3).

1 of 6 evidence gates passing

11 inputs breach the evidence standard and 0 require disclosure. The base case is indicative only until these are cleared.

#GateValueResult
E1

No Low-confidence input relied on in the base case

Register item 5 breached by: Superstructure and façade rates; Office sale price JOD/sqm; Floor-to-floor price premiums; Selling and marketing cost; Substructure cost (14 m level differential); Showroom / lower-floor price; Service charge and Year 1 operations; Parking price per space; Absorption curve.

9 in base caseFAIL
E2

Material revenue inputs have qualified P→M

Still provisional or client-stated: Office sale price JOD/sqm; Floor-to-floor price premiums; Saleable area basis; Showroom / lower-floor price; Parking price per space; Absorption curve.

6 still P/CFAIL
E3

Medium-confidence base-case inputs carry a disclosure

Disclosure missing for: Bank facility terms; Saleable area basis.

2 undisclosedFAIL
E4

Every M-tagged input links to an evidence ID

All market-evidenced inputs trace to the comparable register.

0 unlinkedPASS
E5

Three most material assumptions are evidenced

Ranked by effect on Net Development Profit: Superstructure and façade rates (Low); Office sale price JOD/sqm (Low); Floor-to-floor price premiums (Low).

0 of 3 HighFAIL
E6

Combined downside remains inside available funding

All downside swings applied simultaneously. Coverage below 1.00x means the combined downside cannot be funded.

0.16x coverageFAIL

C · Materiality ranking and evidence register

Every assumption is re-run through the model with its downside swing applied, and ranked by the effect on Net Development Profit. Set the source, confidence and treatment of each input; the gates above update immediately. Amber cells are editable.

#InputSourceConfidenceTreatmentEvidence IDSwing testedΔ NDPΔ RoCΔ Peak gapVerdict
1

Superstructure and façade rates

Cost

Rates +15%

DG Jones cost opinion (±25–30%) and contractor rate sanity calls.

(JOD 663,672)-4.0%(JOD 510,950)BREACH

Low confidence cannot sit in the base case. Move to sensitivity or raise the evidence.

2

Office sale price JOD/sqm

Revenue

Material revenue

Price −10%

Four qualified direct/near-direct Abdoun comparables, adjusted for floor, size and specification.

(JOD 634,326)-5.7%(JOD 317,449)BREACH

Low confidence cannot sit in the base case. Move to sensitivity or raise the evidence.

3

Floor-to-floor price premiums

Revenue

Material revenue

All premiums removed

Paired comparable evidence or repeated broker/valuer confirmation that premiums are achieved.

(JOD 489,022)-4.4%(JOD 244,732)BREACH

Low confidence cannot sit in the base case. Move to sensitivity or raise the evidence.

4

Selling and marketing cost

Revenue

Commission +2pp

Agreed agency terms plus a costed launch and sales-team budget.

(JOD 349,188)-2.6%(JOD 171,744)BREACH

Low confidence cannot sit in the base case. Move to sensitivity or raise the evidence.

5

Substructure cost (14 m level differential)

Cost

Substructure +25%

Completed geotechnical investigation and the DG Jones cost opinion due 16 Oct 2026.

(JOD 249,706)-1.6%(JOD 221,245)BREACH

Low confidence cannot sit in the base case. Move to sensitivity or raise the evidence.

6

Land value

Cost

Land +10%

Owner title and acquisition records.

(JOD 218,452)-1.4%(JOD 205,565)OK

Evidenced input — may support the base case.

7

Bank facility terms

Finance

Rate +2pp

Indicative term sheet from the lending bank.

(JOD 182,729)-1.1%(JOD 58,473)BREACH

Medium confidence requires a written disclosure before it may sit in the base case.

8

Saleable area basis

Revenue

Material revenue

GFA −5%

Controlled architect area schedule reconciled to the legal saleable basis.

+JOD 165,282+1.1%+JOD 124,299BREACH

Material revenue input still tagged C. Must qualify to M before supporting the base case.

9

Showroom / lower-floor price

Revenue

Material revenue

Price −10%

Technically comparable showroom transactions plus operator or specialist broker evidence.

(JOD 136,458)-1.2%(JOD 68,291)BREACH

Low confidence cannot sit in the base case. Move to sensitivity or raise the evidence.

10

Service charge and Year 1 operations

Operations

Operating cost +25%

Benchmarks from managed commercial buildings plus an FM estimate.

(JOD 53,518)-0.3%(JOD 1,486)BREACH

Low confidence cannot sit in the base case. Move to sensitivity or raise the evidence.

11

Parking price per space

Revenue

Material revenue

Price −20%

Comparable evidence on separately sold spaces and buyer willingness to pay.

(JOD 37,905)-0.3%(JOD 18,970)BREACH

Low confidence cannot sit in the base case. Move to sensitivity or raise the evidence.

12

Absorption curve

Programme

Material revenue

Sales delayed two quarters

Project-level sell-through from comparable launches; broker pipeline and time-on-market data.

JOD 00.0%(JOD 2,021,376)BREACH

Low confidence cannot sit in the base case. Move to sensitivity or raise the evidence.

Combined downside — every swing applied together

Net development profit

(JOD 5,940,019)

Return on cost

-47.1%

Peak funding gap

(JOD 7,967,927)

This is not a forecast. It is the arithmetic consequence of every assumption landing at the unfavourable end of its tested range at once, and is shown to size the exposure carried by the evidence still outstanding.