PROJECT IL BOSCO  |  CONFIDENTIAL  |  NOT FOR EXTERNAL CIRCULATION
⚠ PROVISIONAL DATA — All figures subject to DGJ cost opinion (16 Oct 2026)

Cumulative Cash Position & Net Cash per Quarter

Closing cumulative position: (JOD 3,146,511). Peak funding requirement of (JOD 4,645,265) occurs at Q4'27.

Absorption Profile — Units Sold per Quarter

Drives the receipt timing. Total scheduled: 40 of 40 units.

Quarterly Breakdown

QuarterUnits SoldReceiptsOutflowsNet CashCumulative
Q4'26003,212,491-3,212,491-3,212,491
Q1'274808,5501,438,968-630,418-3,842,908
Q2'2761,212,8261,136,09276,733-3,766,175
Q3'2761,212,8261,469,292-256,467-4,022,642
Q4'27▼ PEAK4808,5501,431,173-622,623-4,645,265
Q1'2851,010,688921,23689,452-4,555,813
Q2'2851,010,688336,596674,092-3,881,722
Q3'2851,010,688502,026508,662-3,373,060
Q4'2851,010,688345,790664,898-2,708,162
Q1'2900136,338-136,338-2,844,500
Q2'2900122,687-122,687-2,967,187
Q3'2900122,687-122,687-3,089,874
Q4'290056,638-56,638-3,146,511
TOTAL408,085,50411,232,015-3,146,511

Outflows by Cost Category

CategoryQ4'26Q1'27Q2'27Q3'27Q4'27Q1'28Q2'28Q3'28Q4'28Q1'29Q2'29Q3'29Q4'29Total
Land & Acquisition2,280,000————————————2,280,000
Substructure486,000324,000———————————810,000
Superstructure—584,640584,640584,640584,640584,640———————2,923,200
MEP——212,224212,224218,655————————643,104
Fitout / Specialist———134,400134,400————————268,800
Parking191,100191,100———————————382,200
Common / External———198,800198,800————————397,600
Preliminaries67,13667,13667,13667,13667,13667,13667,13667,136—————537,090
Soft Costs133,650133,650133,650133,65089,10089,10089,10089,100—————891,000
S&M and CX54,60554,60554,60554,60554,60554,60554,60554,60554,60527,30213,65113,651—546,046
Finance Costs—83,83783,83783,83783,837125,756125,756125,756125,75652,39852,39852,398—1,047,963
Handover———————165,430165,430————330,860
Year 1 Ops—————————56,63856,63856,63856,638226,550
TOTAL OUTFLOWS3,212,4911,438,9681,136,0921,469,2921,431,173921,236336,596502,026345,790136,338122,687122,68756,63811,232,015

Funding Structure

All fields editable — finance cost and the funding gap recalculate.

Islamic Bank Facility
%
%
%
Investor Tranche
%
Owner Equity
Facility requiredJOD 9,136,450
Arrangement feeJOD 137,047
Bank finance costJOD 730,916
Investor returnJOD 180,000
Total finance costJOD 1,047,963

Peak Funding Gap: (JOD 4,645,265) — committed funding JOD 1,237,047 — coverage 26.6%

⚠ FUNDING SHORTFALL — project cannot proceed without additional funding

Coverage follows the V1 workbook convention, which counts the arrangement fee rather than the drawn facility as available funding. Flagged for correction in V2.

GDV

JOD 8.33M

— at base

TDC

JOD 11.28M

— at base

Net Dev Profit

(JOD 3.20M)

— at base

Peak Funding Gap

(JOD 4.65M)

— at base

Return on Cost

-28.3%

Target ≥ 15%

Verdict

NOT VIABLE